Big Beaver Road (PERMIT PROJECT) | Westbound Big Beaver Road, just west of I-75. | Troy | AT&T utility work. | The westbound left (inside) lane is closed just west of I-75. Traffic is shifted to the open lanes in the work zone. | No. | AT&T | 7/17 | Early September | Permit Work and Short-Term Road Closures |
Cooley Lake Road culvert replacement over the Huron River | Carroll Lake Road and Bogie Lake Road (the culvert is just west of Carroll Lake Road). | Commerce Township and White Lake Township | Replace culverts with pre-cast concrete bridge, asphalt paving in the vicinity of the new bridge, new guardrail, storm sewer/drainage improvements and new concrete curbs and gutters in the vicinity of the bridge. | The road is closed between Carroll Lake Rd and Oxbow Lake Rd. Residential access maintained east and west of the work. | Carroll Lake Rd to Wise Rd to Bogie Lake Rd, back to Cooley Lake Rd and vice versa. | Anlaan Construction | 7/10 | Late October | Cooley Lake Road Culvert Replacement |
Davisburg Road/Broadway Road (PERMIT PROJECT) | Andersonville Road to Hickey Avenue | Springfield Township | Mill Pond dam removal, channel restoration, culvert installation and asphalt paving. | Yes, the road will completely close to traffic. | Andersonville Rd to White Lake Rd to Dixie Hwy, back to Davisburg Rd/Broadway Rd and vice versa. | Anglin Civil, on behalf of Springfield Township | September TBA | December TBA | Davisburg Road/Broadway Road (Mill Pond/Dam Removal) |
Dutton Road Bridge Replacement | Between the north and south legs of Livernois Road over Paint Creek. | Rochester Hills and Oakland Township | Bridge replacement over the Paint Creek. Work also includes asphalt paving in the vicinity of the bridge, shoulder paving on the north side of Dutton Rd to the Paint Creek Trail parking lot and new curbs, gutters and guardrails. | Dutton Rd, between the north and south legs of Livernois Rd, is closed to traffic. | Dutton Rd to Brewster Rd to Tienken Rd to Orion Rd, back to Dutton Rd and vice versa. | Grand River Construction, Inc. | 7/26 | Early November | Dutton Road Bridge Replacement |
East Avon Road, Dequindre Road to 23 Mile Road (PERMIT PROJECT)
| 23 Mile Road and Dequindre Road
| Rochester Hills and Shelby Township
| Great Lakes Water Authority (GLWA) water infrastructure improvements. The project includes reconstruction and widening of East Avon Rd and roundabout construction at 23 Mile and Dequindre Rd.
| No.
| No.
| GLWA
| 12/5/22
| COMPLETE | Great Lakes Water Authority |
Elizabeth Lake Road/Oxbow Lake Road intersection (PHASE 2) | Elizabeth Lake Road/Oxbow Lake Road intersection and resurfacing work on Elizabeth Lake Road from Teggerdine Road to Oxbow Lake Road | White Lake Township | Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, resurfacing between the two roundabouts, and curb and gutter installation. | Yes, the intersection is closed. | Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa. | Fonson Company Inc. | 6/19 | Early September | Elizabeth Lake Road Roundabouts (White Lake Township) |
Greenfield Road (Southbound) | 10 Mile Road to just north of 9 Mile Road | Southfield | Concrete removal and replacement. | Southbound Greenfield Rd is closed to traffic. Business access maintained. Northbound Greenfield Rd remains open. | 10 Mile Rd to Coolidge Hwy to 9 Mile Rd, back to Greenfield Rd. | Cipparrone Contracting, Inc. | 8/14 | Late September | Concrete Repairs |
Greenfield Road/Normandy Road/Beverly Road intersection
| Greenfield Road/ Normandy Road/ Beverly Road intersection
| Village of Beverly Hills and Royal Oak
| Construction of a "compact" one-lane roundabout, reconstruction of .19 miles of Normandy and Greenfield roads, drainage improvements, new sidewalks, permanent closure of Beverly Court at Greenfield Road, and new curbs and gutters.
| No.
| No.
| DiPonio Contracting
| 6/12
| COMPLETE | Greenfield/Normandy/Beverly Roundabout |
John R Road | 14 Mile Road to Maple Road | Troy | Resurfacing work that includes removing existing pavement, paving with asphalt, traffic signal upgrades, replacing bad concrete slabs at the John R/Maple Rd intersection, minor drainage improvements, new guardrail and curb and gutter replacements. | No. Two-way traffic maintained on John R throughout the work. Business access maintained. | No | Pro-Line Asphalt | 8/23 | 11/9 | John R Road, 14 Mile Road to Maple Road |
Novi Road | Nine Mile Road to Ten Mile Road | Novi | Asphalt resurfacing, some widening, Americans with Disabilities Act-compliant crosswalks, culvert/sewer crossing replacements, drainage improvements, traffic signal upgrades, concrete replacement and left-turn lane extension south of 10 Mile Rd. | Yes, northbound Novi Rd is closed. Southbound Novi Rd is open to traffic for the project’s duration. | The detour for the northbound closure is Nine Mile Rd to Meadowbrook Rd to Ten Mile Rd, back to Novi Rd. Residential and business access maintained utilizing SB Novi Rd. | Springline Excavating LLC | 3/20 | Late fall | Novi Road, Nine Mile to Ten Mile Road |
Oakwood Road/Hadley Road intersection
| Oakwood Road/Hadley Road intersection
| Brandon Township
| Intersection safety improvements including extending some turn lanes on Oakwood Rd, replacement of culvert under the road, widening Oakwood Rd shoulders, storm sewer/drainage improvements, new curbs and gutters.
| No.
| No.
| Zito Construction
| 6/19
| COMPLETE | Oakwood Road/Hadley Road intersection |
Orchard Lake Road | Middlebelt Road to south of Commerce Road | Keego Harbor, Orchard Lake Village, Sylvan Lake and West Bloomfield Township | Paving with asphalt, converting the road to three through lanes with continuous center left-turn lane, some reconstruction, sidewalk upgrades, Americans with Disabilities Act-compliant crosswalks and traffic signal upgrades. | No. Two-way traffic and access to businesses maintained. | No. | Cadillac Asphalt | 7/10 | Mid-November | Orchard Lake Road, Commerce Road to Middlebelt Road |
Orion Road/Stoney Creek Road/Conklin Road intersection | Orion Road/Stoney Creek Road/Conklin Road intersection. | Orion Township | Safety improvements that include roundabout construction at the Orion Rd/Stoney Creek Rd intersection, a "T" intersection at Conklin Rd/Orion Rd, asphalt paving, drainage improvements, ADA-compliant pedestrian crosswalks, and intersection lighting. | Yes, the intersection is closed. | Adams Rd to Silverbell Rd to Lapeer Rd (M-24) to Flint St to Miller Rd, back to Orion Rd and vice versa. | Pro-Line Asphalt | 8/7 | Early November | Orion/Stoney Creek/Conklin Roundabout |
Oxbow Lake Road | Elizabeth Lake Road to Cooley Lake Road (work is south of the Cedar Island Lake access) | White Lake Township | Culvert removal and replacement that also includes asphalt paving over the vicinity of the culvert, new wing and headwalls and new guardrails. | Yes, the road will close in the vicinity of the culvert. Residential and business access maintained north and south of the road closure. Cedar Island Lake access maintained north of the project. | Cooley Lake Rd to Bogie Lake Rd to Highland Rd (M-59) to Teggerdine Rd, back to Elizabeth Lake Rd and vice versa. | Superior Contracting, Inc. | 9/5 | 11/15 | Oxbow Lake Road Culvert Replacement over the Huron River |
Preservation Overlays (Simple Resurfacing) | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No, expect traffic delays. At least one lane will remain open on each road during the work with flaggers directing traffic. | No | Cadillac Asphalt and Ace-Saginaw Paving | 4/25 | Fall, TBA | Simple Resurfacing (Preservation Overlays) |
Spot Resurfacing | Various heavier traveled roads in Oakland County | Various | Milling (grinding) of pavement on smaller sections of roads and paving with asphalt. Paving work is weather-dependent. | No, work is done with flaggers directing traffic | No | Florence Cement and Pro-Line Asphalt | 5/2 | TBA | Spot Resurfacing |
Ten Mile Road (PHASE 2) | Haggerty Road to Meadowbrook Road | Novi | Resurfacing with asphalt, safety improvements (continuous center left-turn lane), Americans with Disabilities Act-compliant crosswalks, a sidewalk on the south side of Ten Mile Rd, traffic signal upgrades, shoulder widening, curb and gutter repairs/replacement. | Yes, the road is closed to westbound traffic and remains open to eastbound traffic. Business and residential access maintained. | Westbound traffic detour is Haggerty Rd to Grand River Ave to Meadowbrook Rd, back to Ten Mile Rd. | Toebe Construction | 5/22 | Fall (road is expected to reopen to two-way traffic approximately early September) | Ten Mile Road |
Twelve Mile Road (PERMIT PROJECT) | Dartmouth Road to Stephenson Hwy. | Madison Heights | MDOT is constructing a diverging diamond interchange in conjunction with I-75 construction, 8 Mile Rd (M-102) to north of 13 Mile Road. | Yes | 12 Mile Rd to John R Rd to 13 Mile Rd to Stephenson Hwy., back to 12 Mile Rd and vice versa. | MDOT | 2/24 | 8/31 | Modernize 75 |
Waldon Road (PHASE 1) | Baldwin Road to Clintonville Road | Independence Township and Orion Township | A two-year project that includes gravel road paving with asphalt, replacement of culverts, shared-use pathway along a section of Waldon Rd, paved road shoulders and stream improvement. A roundabout at Clintonville/Waldon Rd will be built in 2024. | Yes, the road is closed. Access to homes and businesses maintained. | Baldwin Rd to Maybee Rd to Clintonville Rd, back to Waldon Rd and vice versa. | Dan's Excavating | 6/19 | Mid-November (Phase 2 construction will start in early 2024, date TBA) | Waldon Road, Clintonville to Baldwin Road |
Walton Blvd. | Clintonville Road to the Pontiac city limits | Waterford Township | Removal of pavement, paving with asphalt, some curb/gutter repairs, traffic signal upgrade at Walton/Silver Lake Rd intersection and Americans with Disabilities Act-compliant crosswalks. | No. Two-way traffic maintained on Walton Blvd. | No. | Florence Cement | 6/6 | Mid-November | Walton Blvd., Clintonville Road to the Pontiac city limits |