PROJECT LIMITS/COMMUNITY/FUNDING:
PROJECT LIMITS: Elizabeth Lake Road/Teggerdine Road and Elizabeth Lake Road/Oxbow Lake Road intersections
COMMUNITY: White Lake Township
FUNDING: The approximate $2.39 million project is funded by the Road Commission for Oakland County and White Lake Township
PUBLIC MEETING:
DATE: January 11, 2022
TIME: 4:30 p.m. - 7 p.m. (start time updated)
LOCATION: Oxbow Elementary School, 100 Oxbow Lake Road, White Lake Township
MEETING INFORMATION: No formal presentation. R.C.O.C. staff will be available to review and discuss plans with participants
REQUIREMENTS: Since the meeting is being held at public school, participants must wear a mask per school policy.
Meeting and project information flyer
PROJECT DETAILS:
The approximate $2.39 million project includes:
- Conversion of the three-way Elizabeth Lake Road/Teggerdine Road intersection, now controlled by stop signs, to a single-lane roundabout.
- Conversion of the three-way Elizabeth Lake Road/Oxbow Lake Road intersection, now controlled by stop signs, to a compact roundabout.
- Repaving of both roads in the vicinity of the roundabouts with asphalt.
- Installation of curbs and gutters, sidewalks, Americans with Disabilities Act (ADA)-compliant pedestrian crosswalks and street lighting at the roundabouts.
- Improvements to storm sewers and drainage.
- Milling and paving Elizabeth Lake Road between the roundabouts with the addition of four-foot road shoulders.
- Utility relocation, expected to start in the winter of 2022.
CONTRACTOR/TIMELINE/ROAD CLOSURE:
CONTRACTOR: Fonson Company, Inc.
CONTRACTOR WEBSITE: http://www.fonsoninc.com/
PROJECT START: March 13
PROJECT COMPLETION: September 1
ROAD CLOSURE: Yes. Access to homes and businesses will be maintained throughout the construction.
- STAGE ONE: Starting March 13, the Elizabeth Lake Road/Teggerdine Road intersection is open for local and residential traffic only.
- STAGE TWO: The Elizabeth Lake Road and Oxbow Lake Road intersection is expected to close June 19 (after the completion of the school year) through early September for roundabout construction.
DETOUR: Elizabeth Lake Road to Williams Lake Road to Pontiac Lake Road to Highland Road (M-59) to Bogie Lake Road to Cooley Lake Road to Oxbow Lake Road and vice versa.
ADDITIONAL INFORMATION:
40th roundabout opens in White Lake Twp at the Elizabeth Lake Road/Oxbow Lake Road intersection
Elizabeth Lake Road/Oxbow Lake Road intersection to close on June 19 for roundabout construction
Roundabout construction in White Lake Township to start on March 13 with the closure of the Elizabeth Lake Rd/Teggerdine Rd intersection
Lasco Press article on the construction of roundabouts on Elizabeth Lake Road
Hometown Life article on the Elizabeth Lake Road construction of roundabouts
Roundabout Resources For Roundabouts For Roundabouts
Elizabeth Lake Road project delayed until 2023
Elizabeth Lake Road Roundabouts Project Information Flyer
Spinal Column article about the project