Brown, Giddings and Silver Bell roads | M-24 (Lapeer Road) to Jamm Road | Auburn Hills and Orion Township | Pavement removal, asphalt paving, widening on Brown Rd, drainage improvements, traffic signal installation/modernization, side street and driveway approach reconstruction, new guardrail and pavement markings. | Silver Bell Rd remains open with one lane in each direction. There will be separate closures of Brown Rd and Giddings Rd. Dates will be announced. | Detours will be announced for separate closures of Brown Rd and Giddings Rd. | Dan's Excavating | 4/16 | Mid-November | Brown, Giddings and Silver Bell roads |
Davisburg Road/Broadway Road (PERMIT PROJECT) | Andersonville Road to Hickey Avenue | Springfield Township | Mill Pond dam removal, channel restoration, culvert installation and asphalt paving. | The road is temporarily open to traffic. | The road will close again in the spring, date TBA. The detour will be Andersonville Rd to White Lake Rd to Dixie Hwy, back to Davisburg Rd/Broadway Rd and vice versa. | Anglin Civil, on behalf of Springfield Township | 10/2/23 | The road temporarily reopened to traffic on March 12 (the road will close again in the spring for asphalt paving and Mill Pond work, a date will be announced) | Davisburg Road/Broadway Road (Mill Pond/Dam Removal) |
Dequindre Road (PERMIT PROJECT) | Hamlin Road to Avon Road | Rochester Hills and Shelby Township | Great Lakes Water Authority 96-inch water transmission pipe installation, reconstruction of Dequindre Road and replacement of the Honeywell Ditch culvert with a concrete structure. | Yes, business and residential access maintained. | Hamlin Rd to John R Rd to Avon Rd, back to Dequindre Rd and vice versa. | Ric-Man Clark Joint Venture on behalf of the Great Lakes Water Authority | 11/6/23 | Late November | Great Lakes Water Authority |
Grand River Avenue | Napier Road to Wixom Road | Lyon Township and Wixom | Grinding pavement, resurfacing with asphalt, some reconstruction, installation of a continuous center left-turn lane between Napier and 12 Mile, traffic signal upgrades, Americans with Disabilities Act-compliant crosswalks and some road shoulder paving. | Two-way traffic is maintained on Grand River Ave. | No, Grand River Ave will remain open to two-way traffic. | Fonson | 4/1 | Late August | Grand River Avenue, Napier to Wixom Road |
*Napier Road at Grand River Avenue (part of the Grand River Avenue, Napier to Wixom Road project) | Napier Road at Grand River Avenue | Wixom and Lyon Township | Intersection construction that is part of the Grand River Ave, Napier to Wixom Rd, project. | Napier Rd will close at Grand River Ave for approximately 28 days. Grand River Ave will remain open to two-way traffic. | Grand River Ave to Beck Rd to Ten Mile Rd, back to Napier Rd and vice versa. | Fonson | 4/29 | Late May | Grand River Avenue, Napier to Wixom Road |
*Heights Road Westbound (PERMIT PROJECT) | Lapeer Road (M-24) to Odanah Avenue | Orion Township | Sanitary sewer and water utility work for private development. | Yes, the road is closed. Residential access maintained east and west of the closure. The closure is approximately 400 feet west of Lapeer Rd. | Lapeer Rd (M-24) to Clarkston Rd to Pinetree Rd to Heights Rd to Odanah St to Kimberly Rd, back to westbound Heights Rd. | Mystic Cove Orion, LLC | 4/15 | 4/19 | Permit Work and Short-Term Road Closures |
Indianwood Road Culvert Replacement | Lapeer Road (M-24) to Joslyn Road | Orion Township | Utility relocation work, upgrades to township water and sewer infrastructure, replacement of the culvert under the road that carries Paint Creek, storm sewer improvements and asphalt paving over the vicinity of the culvert. | Yes, the road is closed between Abseguami Trl and Fernhurst Dr. | Joslyn Rd to Clarkston Rd to Lapeer Rd, back to Indianwood Rd and vice versa. | Dan's Excavating | 1/16 | 10/5 | Indianwood Road Culvert Replacement over the Paint Creek |
*Long Lake Road Culvert Replacement | Eastways Road to Squirrel Road (culvert is just east of Eastways Road) | Bloomfield Hills | Remove and replace the culvert under the road that carries the Rouge River. The work also includes paving in the vicinity of the culvert, new signage, guardrail and pavement markings. | Yes, the road will close just east of Eastways Rd. Residential and business access maintained east and west of the road closure. | Long Lake Rd to Squirrel Rd to Square Lake Rd (just south of I-75 Business Loop/Square Lake Rd) to Eastways Rd, back to Long Lake Rd and vice versa. | DiPonio Contracting | June, TBA | August, TBA (once Long Lake Rd reopens to traffic, the contractor will close Eastways Rd, just north of Long Lake Rd, to remove and replace the second culvert). | Long Lake Road and Eastways Road Culvert Replacements |
Pontiac Lake Road Bridge Replacement over the Clinton River | Airport Road and Crescent Lake Road (between Irwin Drive and North Pine Grove Avenue) | Waterford Township | Remove and replace the structure over the Clinton River. The project includes a new pre-cast concrete culvert, headwalls, wing walls, watermain relocation, storm sewer upgrades, pedestrian access improvement and asphalt paving in the vicinity of the bridge. | Yes, Pontiac Lake Rd will close to vehicle and pedestrian traffic between Irwin Dr and North Pine Grove Ave. Pedestrian and business access maintained east and west of the bridge work. | Airport Rd to Highland Rd (M-59) to Crescent Lake Rd, back to Pontiac Lake Rd and vice versa. | Z Contractors Inc. | 6/3 | 10/18 | Pontiac Lake Road Bridge Replacement over the Clinton River |
*Preservation Overlays (Simple Resurfacing) | The work will be done on just over 46 miles of heavier-traveled roads. | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No, expect traffic delays. Roads are expected to remain open with flaggers directing traffic. | No. | No. | Cadillac Asphalt | 4/22 | TBA | Simple Resurfacing (Preservation Overlays) |
*Southfield Road | 11 Mile Road to 12 Mile Road | Lathrup Village | Resurfacing project that includes removing the road surface, paving with asphalt, reconstructing some side street approaches, crosswalk improvements, traffic signal modernization at some intersections and extensive intersection construction work. | Southfield Rd will mostly remain open to two-way traffic; expect weekend closures of the 12 Mile Rd/Southfield intersection. 11 Mile Rd will close at Southfield Rd. I-696 ramps to Southfield Rd will close. | For pending detours and intersection full or partial closures information, visit https://www.rcocweb.org/680/Southfield-Road-11-Mile-Road-to-12-Mile- (business access maintained) | Ajax paving | 4/29 | Early summer | Southfield Road, 11 Mile Road to 12 Mile Road |
*Spot Resurfacing | Various heavier traveled roads throughout Oakland County. | Milling (grinding) pavement on roads and paving with asphalt. The work is weather-dependent. | No, expect traffic delays. Roads are expected to remain open with flaggers directing traffic. | No. | No. | Florence Cement Company | 4/22 | TBA | Spot Resurfacing |
Waldon Road (PHASE 2) | Just east of Montclair Drive to Clintonville Road | Independence Township and Orion Township | The remaining work includes gravel road paving with asphalt, replacing a culvert just east of Clintonville Rd, paving road shoulders and realigning curves to improve safety. | Yes, Waldon Rd is closed to through traffic. | Waldon Rd to Baldwin Rd to Clintonville Rd, back to Waldon Rd and vice versa. | Dan's Excavating | 3/8 | Mid-October | Waldon Road, Clintonville to Baldwin Road |
Waldon Road and Clintonville Road roundabout construction (part of the Waldon Road-PHASE 2 project) | Waldon Road/Clintonville Road intersection | Independence Township | Construction of a roundabout at the Waldon Road/Clintonville Road intersection, asphalt paving, culvert replacement and stream realignment. | Yes, starting approximately July 1. | Waldon Rd to Baldwin Rd to Maybee Rd to Sashabaw Rd to Clarkston Rd, back to Clintonville Rd and vice versa. | Dan's Excavating | 7/1 (expected start) | Mid-October | Waldon Road, Clintonville to Baldwin Road |
Walton Blvd. | Adams Road to just east of Livernois Road | Rochester Hills | Removing pavement, paving with asphalt, culvert replacement, minor storm sewer improvements, Americans with Disabilities Act-compliant sidewalk ramps, concrete curb and gutter repairs. | Walton Blvd has one lane open in each direction throughout construction. Business and residential access maintained. | No. | Pro-Line Asphalt | 4/15 | Mid-August | Walton Blvd., Adams to Livernois Road |