Posted on: April 1, 2024

[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS APR. 1 AND APR. 5 OR MIGHT START SHORTLY THEREAFTER

Road-Construction-Update image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between April 1 and April 5 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change daily, and traffic delays can develop in minutes due to weather, emergency situations, etc.

The project list is attached.                                         

Additional information about current and upcoming projects can also be viewed on the RCOC website:   RCOC 2024 Road Construction  (https://www.rcocweb.org/189/Road-Projects). 

    

RCOC Road Construction and Permit Projects (4/1/24 update)

ROAD

PROJECT LIMITS

COMMUNITY

PROJECT DESCRIPTION

CLOSURE

DETOUR

CONTRACTOR

PROJECT START

ESTIMATED COMPLETION

PROJECT INFORMATION

Brown, Giddings and Silver Bell roads

M-24 (Lapeer Road) to Jamm Road

Auburn Hills and Orion Township

Pavement removal, asphalt paving, widening on Brown Rd, drainage improvements, traffic signal installation/modernization, side street and driveway approach reconstruction, new guardrail and pavement markings.

Silver Bell Rd will remain open with one lane in each direction. There will be separate closures of Brown Rd and Giddings Rd. Dates will be announced.

The detour will be announced for separate closures of Brown Rd and Giddings Rd.

Dan's Excavating

4/16

Mid-November

Brown, Giddings and Silver Bell roads

Davisburg Road/Broadway Road (PERMIT PROJECT)

Andersonville Road to Hickey Avenue

Springfield Township

Mill Pond dam removal, channel restoration, culvert installation and asphalt paving.

The road is temporarily open to traffic.

The road will close again in the spring, date TBA. The detour will be Andersonville Rd to White Lake Rd to Dixie Hwy, back to Davisburg Rd/Broadway Rd and vice versa.

Anglin Civil, on behalf of Springfield Township

10/2/23

The road temporarily reopened to traffic on March 12 (the road will close again in the spring for asphalt paving and Mill Pond work, date will be announced)

Davisburg Road/Broadway Road (Mill Pond/Dam Removal)

Dequindre Road (PERMIT PROJECT)

Hamlin Road to Avon Road

Rochester Hills and Shelby Township

Great Lakes Water Authority 96-inch water transmission pipe installation, reconstruction of Dequindre Road and replacement of the Honeywell Ditch culvert with a concrete structure.

Yes, business and residential access maintained.

Hamlin Rd to John R Rd to Avon Rd, back to Dequindre Rd and vice versa.

Ric-Man Clark Joint Venture on behalf of the Great Lakes Water Authority

11/6/23

Late November

Great Lakes Water Authority

Grand River Avenue

Napier Road to Wixom Road

Lyon Township and Wixom

Grinding pavement, resurfacing with asphalt, some reconstruction, installation of a continuous center left-turn lane between Napier and 12 Mile, traffic signal upgrades, Americans with Disabilities Act-compliant crosswalks and some road shoulder paving.

Two-way traffic will be maintained on Grand River Ave. Napier Rd will close at Grand River Ave for reconstruction; date will be announced.

Yes, Napier Rd will close at Grand River Ave for reconstruction. Once closed, the detour is Napier Rd to Ten Mile Rd to Beck Rd, back to Grand River Ave and vice versa.

Fonson

4/1

Late August

Grand River Avenue, Napier to Wixom Road

Indianwood Road Culvert Replacement

Lapeer Road (M-24) to Joslyn Road

Orion Township

Utility relocation work, upgrades to township water and sewer infrastructure, replacement of the culvert under the road that carries Paint Creek, storm sewer improvements and asphalt paving over the vicinity of the culvert.

Yes, the road is closed between Abseguami Trl and Fernhurst Dr.

Joslyn Rd to Clarkston Rd to Lapeer Rd, back to Indianwood Rd and vice versa.

Dan's Excavating

1/16

10/5

Indianwood Road Culvert Replacement over the Paint Creek

*Pontiac Lake Road Bridge Replacement over the Clinton River

Airport Road and Crescent Lake Road (between Irwin Drive and North Pine Grove Avenue)

Waterford Township

Remove and replace the structure over the Clinton River. The project includes a new pre-cast concrete culvert, headwalls, wing walls, watermain relocation, storm sewer improvements pedestrian access improvement  and asphalt paving in the vicinity of the bridge.

Yes, Pontiac Lake Rd will close to vehicle and pedestrian traffic between Irwin Dr and North Pine Grove Ave. Pedestrian and business access maintained east and west of the bridge work.

Airport Rd to Highland Rd (M-59) to Crescent Lake Rd, back to Pontiac Lake Rd and vice versa.

Z Contractors Inc.

6/3

10/18

Pontiac Lake Road Bridge Replacement over the Clinton River

Waldon Road (PHASE 2)

Just east of Montclair Drive to Clintonville Road

Independence Township and Orion Township

Remaining work includes gravel-road paving with asphalt, replacement of a culvert just east of Clintonville Rd, paving road shoulders and realignment of curves to improve safety.

Yes, Waldon Rd is closed to through traffic.

Waldon Rd to Baldwin Rd to Clintonville Rd, back to Waldon Rd and vice versa.

Dan's Excavating

3/8

Mid-October

Waldon Road, Clintonville to Baldwin Road

Waldon Road and Clintonville Road roundabout construction (part of the Waldon Road-PHASE 2 project)

Waldon Road/Clintonville Road intersection

Independence Township

Construction of a roundabout at the Waldon Road/Clintonville Road intersection, asphalt paving, culvert replacement and stream realignment.

Yes, starting approximately July 1.

Waldon Rd to Baldwin Rd to Maybee Rd to Sashabaw Rd to Clarkston Rd, back to Clintonville Rd and vice versa.

Dan's Excavating

7/1 (expected start)

Mid-October

Waldon Road, Clintonville to Baldwin Road

*Walton Blvd.

Adams Road to just east of Livernois Road

Rochester Hills

Removing pavement, paving with asphalt, culvert replacement, minor storm sewer improvements, Americans with Disabilities Act-compliant sidewalk ramps, concrete curb and gutter repairs.

No, the road will have one lane open in each direction for traffic throughout construction. Business and residential access maintained.

No.

Pro-Line Asphalt

April, TBA

TBA

Walton Blvd., Adams to Livernois Road

 *indicates a new project; TBA (To Be Announced)

Road Construction & Permit Projects Update