Milford Road Culvert Replacement

Project location:  Milford Road over the Shiawassee River just east of South Fenton Road (east of railroad tracks)

Community:  Rose Township

Project description:

  • Remove and replace culvert under Milford Road that carries the Shiawassee River
  • Resurface road
  • New guardrail and pavement markings

Project cost:   $850,000

Contractor:  Zito Construction

Contractor Information  

Project start: August 12, 2019  September 3, 2019

Project completion:  Mid-October

Detour:  Yes, residential access will be maintained east of culvert

Detour route: Milford Road to Clyde Road to Hickory Ridge Road to Fenton Road, back to Milford Road and vice versa

Milford Road Culvert location

Prior to construction, Milford Road just east of South Fenton Road and railroad tracks, culvert loca


Additional Information: