May 3, 2021 7:00 AM

GREENFIELD ROAD FROM 13 MILE RD TO 14 MILE RD WILL REMAIN CLOSED UNTIL LATE SEPTEMBER

Consumers Energy will keep Greenfield Road closed to through traffic from 13 Mile Road to 14 Mile Road on the Royal Oak/Beverly Hills border for gas main replacement work until late September.
Consumers had previously expected to reopen the road in late July; however, the delays are due to numerous utility conflicts and delays in receiving necessary pipes to complete the work.
Northbound Greenfield Road remains open for local traffic only with access to homes and businesses maintained. Southbound Greenfield Road will remain closed.
The detour for through traffic is 13 Mile Road to Southfield Road to 14 Mile Road, back to Greenfield Road and vice versa.
The work is being done under a permit issued by the Road Commission for Oakland County (RCOC). This section of Greenfield Road carries approximately 17,860 vehicles per day.

Utility Work
Facebook Twitter Email

Latest Update:

August 30, 2021 6:43 AM

Consumers Energy will keep Greenfield Road closed to through traffic from 13 Mile Road to 14 Mile Road on the Royal Oak/Beverly Hills border for gas main replacement work until late September. 

Consumers had previously expected to reopen the road in late July; however, the delays are due to numerous utility conflicts and delays in receiving necessary pipes to complete the work.   

            Northbound Greenfield Road remains open for local traffic only with access to homes and businesses maintained. Southbound Greenfield Road will remain closed.

The detour for through traffic is 13 Mile Road to Southfield Road to 14 Mile Road, back to Greenfield Road and vice versa.  

            The work is being done under a permit issued by the Road Commission for Oakland County (RCOC). This section of Greenfield Road carries approximately 17,860 vehicles per day.         

            Questions about the extended closure should be directed to Consumers Energy, https://www.consumersenergy.com/contact-us.

Consumers Energy

Prior Updates

July 29, 2021 7:47 AM

Consumers Energy will keep Greenfield Road closed to through traffic from 13 Mile Road to 14 Mile Road on the Royal Oak/Beverly Hills border for gas main replacement work until late August. 

Consumers had previously expected to reopen the road in late July; however, the delays are due to numerous utility conflicts and delays in receiving necessary pipes to complete the work.   

            Northbound Greenfield Road remains open for local traffic only with access to homes and businesses maintained. Southbound Greenfield Road will remain closed.

The detour for through traffic is 13 Mile Road to Southfield Road to 14 Mile Road, back to Greenfield Road and vice versa.  

            The work is being done under a permit issued by the Road Commission for Oakland County (RCOC). This section of Greenfield Road carries approximately 17,860 vehicles per day.