Perry Lake Road over the Clinton River Culvert-COMPLETE

PROJECT LIMITS:  North of Clarkston Road

COMMUNITY: Independence Township

PROJECT COST/INFORMATION:

The $369,500 project is funded by the RCOC.

Project includes:

  • Placing a lining in two 60-inch culverts under Perry Lake Road.
  • Wingwall work
  • Restoration work

The road will remain open to traffic during the work.  Residential access maintained.

CONTRACTOR/TIMELINE:

CONTRACTOR:  Trojan Development Company, Oxford, MI

PROJECT START:  July 31

PROJECT COMPLETION:  August 30