PROJECT TIMELINE/ROAD CLOSURE INFORMATION:
START DATE: August 10
END DATE: Late August for road reopening over Sashabaw Creek; late October for resurfacing work from the culvert location to Clintonville Road (road will remain open to traffic during resurfacing work).
ROAD CLOSURE: Yes, over Sashabaw Creek, culvert removal and replacement is expected to last approximately 21 days. Access to homes and businesses within the project limits will be maintained.
DETOUR (during culvert removal and replacement): Rattek Road to Genoa Road to Pine Knob Lane to Maybee Road to Clintonville Road, back to Mann Road.
*Rattek and Genoa roads and portions of Pine Knob Lane are private streets. RCOC staff has permission to use the private roads for the detour during the work. Any questions and comments can be sent to: design@rcoc.org