PROJECT LIMITS/COMMUNITY:  

PROJECT LIMITS:  Cass Lake Road, south of Cass Elizabeth Lake Road, over the Cass Lake/Otter Lake canal (between Port Cove Drive and Bangor Road)

COMMUNITY:  Waterford Township 

FUNDING/PROJECT INFORMATION:

The approximate $730,000 culvert replacement is funded by the Road Commission for Oakland County.

PROJECT INCLUDES:

  • Remove existing culvert under Cass Lake Road and replace with concrete culvert
  • Replacement of guardrails in the vicinity of the culvert
  • Removal and replacement of 300 feet of asphalt pavement over the culvert
  • Replacement of storm sewer in the vicinity of the culvert
  • Tree removal and utility relocation (expected to start on March 14-March 18; flaggers will direct traffic when necessary)
  • Watermain relocation, administered by Waterford Township (April 2022 (details to be announced); requires full road closure for approximately one month)


CONTRACTOR/TIMEFRAME/DETOUR:

CONTRACTOR:  Superior Contracting 

START DATE:   August 1

END DATE: October 1

WATERFORD TOWNSHIP WATERMAIN RELOCATION START DATE:  April 25

WATERMAIN RELOCATION COMPLETION: May 15

DETOUR (watermain relocation and culvert work):  Cass Elizabeth Lake Road to Cooley Lake Road to Hiller Road, back to Cass Lake Road and vice versa.  Residential and business access are maintained north and south of the culvert and watermain work.  