Maloney Street Bridge Replacement

NELOCATION:  North of Drahner Road, the bridge is over Long Lake and Clear Lake

COMMUNITY:  Oxford Township

FUNDING:  The approximate $2.54 million project is paid for utilizing local bridge funds and the Road Commission for Oakland County dollars.

PROJECT DETAILS: 

  • Replacement of the Maloney Avenue bridge over Long Lake/Clear Lake
  • Reconstruction of one-tenth of a mile of Maloney Avenue with asphalt pavement (work is about 300 feet north and south of the bridge)
  • Upgrading guardrails and traffic signs

SCHEDULE:

  • Utility relocated (expected in the winter and spring of 2022)
  • Minor tree removal (expected March 2-March 4, 2022)
  • Construction start: July 5 
  • Project completion: October 18 Early  November  November 23, 2022 (new bridge open  to traffic)

CONTRACTOR:  F.H. Paschen 

CONTRACTOR WEBSITE: CLICK HERE

TRAFFIC IMPACTS:

Access to all homes will be maintained via a single-lane temporary road. Boat traffic under the bridge will be prohibited during work. 