Frequently Used Special Provisions (FUSP)


GENERAL NOTES

FUSP 
 Code
 TitleDate ModifiedPay ItemNotes
General NotesGeneral Notes01/12/2022 N/AUse on all projects. This is a Word document on General Notes that should be put in the General Plans. Important: You must go through this entire documents and makes changes as appropriate to make it project specific.  
SESC NotesSoil Erosion and Sediment Control (SESC)  08/18/2014 N/AUse on all projects. This is a Word document of the SECS notes that should be put in the SECS sheets.
Culvert/Bridge NotesCulvert and Bridge notes 08/18/2014 N/AUse for bridge and culvert projects.  
FUSP Word Doc TemplateFUSP Word Doc Template07/27/2022N/ARoad Commission for Oakland County FUSP template provided in Microsoft Word .doc format



NOTICE TO BIDDERS

FUSP Code Title Date
 Modified
Pay
Item
 Notes
20PCProgress Clause4/05/2022N/AProgress Clause. For local let projects, rename file "ADMIN4_PCL".
20MOTMaintaining Traffic3/15/2022N/AEntire document has been updated. Read for pay items! Added language about MASH, updated Pedestrian Access an PCMS added Pedestrian Control Devices section.
NB1Project Coordination3/15/2022N/AUpdate to include nearby projects. 
NB2Utility Coordination3/15/2022N/AUpdate utility companies and conflicts per project.
NB3Response to Contractors Inquiry6/21/2021N/AUsed to clarify information that is not clear to the contractor.
NB5Project Special Provisions2/4/15N/AUse when two projects under one contract are similar but separate special provisions for the project/Contract.
SP812APermanent Signage

4/28/2022

N/A

Requires the Contractor to provide shop drawings of all custom face layout permanent signage. Use on all projects with custom face permanent signage.



DIVISION ONE-GENERAL PROVISIONS

FUSP
Code
 TitleDate 
Modified
Pay 
Item
Notes
SP100ADivision I-
General Provisions
(MDOT Let Projects)
5/14/19N/AUse on all projects.  Updated language in 104.13 to include updates to the project inspection form submittal process.
SP100B Work on railroad property-CSX Transportation, Inc.1/4/12N/AUse on projects with work on CSX property.
20SP100CContractor Material Disposal4/22/2021N/AUse on all projects.
20SP104ASubmittals5/17/2021N/AUse on all projects requiring shop drawings for construction. Can be used on bridges, culverts, roads, watermains, concrete, utilities, traffic signals, etc. Make sure review requirements for other items in the proposal are not less than 10 or 20 days.
20SP107APermits and Inspection Fees4/5/2021 Reimbursed Permit Fees (Dlr)Use this special provision in lieu of the Notice to Bidders "permits and fees to be reimbursed for permit fees". If you don't have money in these permits then use this special provision, but delete the pay item line.
12SP108ALocked Incentive Date3/23/16Locked incentive date (DIR)Used on Projects with incentive dates.



DIVISION TWO-EARTHWORK

FUSP
Code
 TitleDate 
Modified
Pay 
Item
Notes
SP201A
Merchantable Timber4/14/2021N/AThis specification only has to do with Wood Disposal Agreements and Merchantable Timber. If your project is removing trees with diameter 8" or more this FUSP must be included.
SP201BClearing, RCOC4/14/2021Clearing, RCOC (Acre)
Clearing, RCOC (Syd)
Changes clearing limits from MDOT's 10 ft to 3 ft beyond Slope Stake Line or ROW. Include in every project in which the contractor will be removing vegetation as well as stumps. 
SP201CGrubbing, RCOC4/14/2021Grubbing, RCOC (Acre)
Grubbing, RCOC (Syd)
This spec shall be used on projects where trees were previously removed as a precaution to protect Federally protected species. Consultants should not use this spec unless authorized by RCOC. 

SP201DClearing, Modified, RCOC 4/14/2021Clearing, Modified, RCOC (Acre)
Clearing, Modified, RCOC (Syd)
For use in the tree contract. This spec shall be used on projects where trees and clearing must be done prior to the start date of the project under a separate tree contract. Consultants should not use this spec unless authorized by RCOC. 
SP202A Tree, Rem, _ inch to _ inch, RCOC 4/14/2021Tree, Rem, _ inch to _ inch, RCOC (Ea) For use in the tree contract. This spec shall be used on projects where specific tree removal must be done prior to the start date of the project under a separate tree contract. Consultants should not use this spec unless authorized by RCOC. 
SP203ASewer, Abandon4/14/2021Sewer, Abandon (Ft)Use this spec in conjunction with Flowable Fill, Non-Structural (Cyd) and Sewer, Bulkhead, _ inch (Ea).

SP204ACurb Head Removal  4/14/2021 Curb Head, Rem (Ft)To be used on concrete overlay projects only. 
SP204BRemoval of Utilities4/14/2021Gas Utility, Rem (Ft)
Telephone Utility, Rem (Ft)
Electric Utility, Rem (Ft)
Water Main, Rem (Ft)
Use in any projects which require the removal of significant utilities. Consult with RCOC before use.  
SP204CExploratory Investigation, Utility2/17/2022Exploratory Investigation, Utility, RCOC (Cyd)
Exploratory,  Investigation, Utility, Vertical, RCOC (Foot)
This work shall be completed where the the existing location of potential underground conflicts with proposed work cannot be readily identified horizontally and/or vertically by the utility owner.
SP204DWood Post Removal 4/14/2021Wood Post, Rem (Ea)This spec is to be used to remove wood bollard posts when Excavation, Earth is not included in the contract. Do not use this spec if Excavation, Earth in included in the contract. 
SP205ADitching, RCOC4/14/2021Ditching, RCOCThis spec is only to be used if relocating a ditch or constructing a new ditch. If performing ditch maintenance use the standard MDOT pay item. Include detail in plans. 
SP205BExcavation, Earth, RCOC4/14/2021Excavation, Earth, RCOC (Syd)This spec is to be used on projects which have driveway, side street, or sidewalk reconstruction. 
SP205CSubgrade Undercutting4/14/2021Subgrade Undercutting, 21AA (Cyd) 
Subgrade Undercutting, 3 by 1 (Cyd)
Subgrade Undercutting, 6A (Cyd)
If used in contract use a minimum of 500 Cyd as a directed quantity. For Subgrade, Undercutting, Class II use MDOT Std Pay item. You will not be able to use geotextiles with sand however. Coordinate with RCOC whether to include Geotextile Separator, Non-Woven and/or Road Grade Biaxial Geogrid 
SP206ABackfill, Select, RCOC4/14/2021Backfill, Select, RCOC (Cyd)Use this with MSE Walls and Gabion Wall Special Provisions. Specifies Contractor testing. 
SP208ASoil Erosion and Sediment Control4/14/2021Erosion Control, Check Dam, Stone RCOC (Ft) 
Erosion Control, Silt Fence, RCOC (Ft)
Erosion Control, Inlet Protection, Fabric Drop, RCOC (Ea)
Erosion Control, Inlet Protection, Geotextile and Stone, RCOC (Ea)
Erosion Control, Inlet Protection, Sediment Trap, RCOC (Ea)
Mulch, Temp, Special, RCOC (Syd)
Mulch, Temp. Regular, RCOC (Syd)
Use on all projects.
SP208BMaintaining Stream Flow4/14/2021Maintaining Stream Flow (LSUM)This work is included in the MDOT Culvert Pay item. Only use when not using MDOT's pay item.



DIVISION THREE- BASES

FUSP
Code
TitleDate 
Modified
Pay
Item 
Notes
SP301ACoarse Aggregate, 3 by 13/27/2021Coarse Aggregate, 3 by 1 (Cyd)Generally used for ground improvement beneath culverts. Coordinate use with RCOC.
SP302AAggregate Base Course10/27/20Aggregate Base, __inch, 21AA RCOC (Syd)
Aggregate Base, LM, 21AA, RCOC (Syd)
Agregate Base, 21AA, RCOC (Ton)
Use on any projects requiring  aggregate base course. This spec prohibits the use of crushed concrete. 
SP302BAggregate Base Conditioning10/27/2020Aggregate Base, Conditioning, RCOC (Syd)This spec shall be used when HMA base crushing only. 
SP303AOpen-Graded Drainage Course3/27/2021Open-Graded Dr Cse, __ inch, RCOC (Syd) 
Open-Graded Dr Cse, CIP, RCOC (Cyd)
Use on all projects with open graded drainage course. Prohibits the use of crushed concrete and has additional requirements for seasonal shutdowns and sampling verses MDOT pay items. 
SP305AHMA Base Crushing and Shaping3/27/2021HMA Base, Crushing and Shaping, RCOC (Syd)Has information on max thickness and material hauling verses MDOT pay item. Coordinate use with RCOC.
SP307AAggregate Approach and Shoulder10/27/2020Approach, 21AA __inch (Syd)
Approach, 21AA (Ton)
Shoulder, 21AA __inch (Syd)
Shoulder, 21AA (Ton)
Use on all aggregate driveway approaches and shoulders. Prohibits the use of crushed concrete. 



DIVISION FOUR-DRAINAGE

FUSP 
Code
TitleDate
Modified
Pay
Item
 Notes
SP401A Pipe Culverts4/08/2022Culv, Cl F, _ inch, RCOC (Ft)
Culv, Cl F, 12 inch, RCOC (Ft)
Culv, Cl F, 15 inch, RCOC (Ft)
Culv, CSP Arch, Cl IV, _ (Span) inch x _ (Rise) inch, RCOC (Ft)
Use on all projects in which there are metal cross culverts. If there is a culvert with less than 3 ft of cover and is under the influence of the road,  concrete Cl E pipe should be used. 
SP402AMaintaining Storm Drainage3/28/2021Maintaining Storm Drainage (Ea)Generally used when maintaining storm from old system to new during staging operations. Consult with RCOC on use. 
SP402BTemporary Storm Sewer Bulkhead3/27/2021Sewer, Bulkhead, Temp, RCOC (Ea)Shall be used for temporary bulkheads for part width construction.
SP403AAdjustment and Reconstruction of Public Utilities - Department of Public Works and Other Utility Structures 3/29/2022Public Utility Structure Cover, Adj, Case _ (Ea)
Public Utility Structure, Adj, Add Depth (Ft)
Public Utility Structure Cover (Ea)
Public Utility Structure, Temp Lowering (Ea)
Use this Spec for all DPW and other public utilities structure adjustments. Basically use for all structures other than drainage structures, which is an MDOT pay item.
SP403BDr Structure Cover, Adj, Case 1, RCOC and Public Utility Structure, Adj, Case 1, RCOC3/29/2022Dr Structure Cover Adj, Case 1, RCOC (Ea)
 Public Utility Structure Cover, Adj, Case 1, RCOC (Ea)
This spec is for Case 1 adjustments in roadway pavement areas. Use this spec if placing poured concrete ring around the structure cover that is flush with the finished road grade. Coordinate use with RCOC. 
SP403CHydrodynamic Separator Structure4/13/2021Hydrodynamic Separator Structure, _ cfs (Ea)Generally used when outletting storm water into a lake or stream. Coordinate use with RCOC. Fillable word document that requires editing to make it project specific. 
SP403DSediment Trap Outlets3/27/2021Sediment Trap, _ inch dia Outlet (Ea)Coordinate use with RCOC.
SP404AUnderdrains3/28/2021Underdrain, Subgrade, Open-Graded, 6 inch, RCOC (Ft)Use this spec for all open graded, 6" underdrain. Include detail in plans if using. 



DIVISION FIVE-HMA

Use an all projects with HMA. 

FUSP
Code
TitleDate
Modified 
Pay
Item
Notes
SP501AAcceptance of Hot Mix Asphalt (HMA)4/20/2021N/A Use on all projects with HMA.
SP501B HMA Plant Testing Lab 3/28/2021 N/A Use on all projects with HMA.  
SP501CPlant Produced Hot Mixed Asphalt (HMA)3/26/2021N/AUse on all projects with HMA. 
SP501D Recycled Hot Mix Asphalt Mixtures 4/20/2021 N/AUse on all projects with HMA.  
SP501EJoint, HMA Plane of Weakness3/28/2021Joint, HMA Plane of Weakness (Ft)This specification must be used with a standard detail, saw cut depth will vary with mat thickness. 
SP501FVoid Reducing Asphalt Membrane 3/28/2021Void Reducing Asphalt Membrane (Ft)Use on leveling course to improve surface joint performance. Consult with RCOC Design/Construction before using. Revision based on application rates.
SP501GCold Milling Pavt3/28/2021Cold Milling Pavt (Syd)Use on overlays over concrete pavement, or when only small amounts of concrete are present. Use MDOT pay item if only removing asphalt. 
SP501HHMA Approach3/28/2021HMA Approach (Commercial) (Ton)
HMA Approach (Residential) (Ton)
HMA Approach (Sidestreet) (Ton)
Use on all projects that will be reconstructing asphalt driveways. Include detail in plans.
SP501JPavement Cleaning3/28/2021Pavt, Cleaning, RCOC (LSUM)Use on all projects. 



DIVISION SIX-PORTLAND CEMENT CONCRETE PAVEMENTS

FUSP
Code
TitleDate
Modified
Pay
Item
Notes
SP602AConcrete Pavement Joint Layout 4/6/2021N/AUse on concrete overlays. For regular concrete projects, use the MDOT pay item.
SP602CTexturing Concrete Pavement by Carpet Dragging 4/5/2021N/ACoordinate with RCOC before using this spec. 
SP602EPavement Gapping4/6/2021Pavt Gapping, RCOC (Ft)Use on concrete overlays. For regular concrete projects, use the MDOT pay item.
SP602FConcrete Pavement with Integral Curb, Miscellaneous4/6/2021Conc Pavt with Integral Curb, Misc, Nonreinf, _ inch (Syd)Generally used on concrete commercial approaches and side streets. Include drive/approach details in plan set.
SP602GDecorative Concrete Pavement 4/6/2021Conc Pavt, Misc, Decorative Colored, _ inch (Syd)Coordinate with Project Engineer before using this spec. Requires editing to make project specific. 
SP602HConcrete Pavement Cracking and Seating4/6/2021Concrete Pavement Cracking and Seating (Syd)Use on HMA overlay projects when paving over existing concrete pavement.
SP603APavement Sawing, Full Depth4/6/2021Pavt Sawing, Full Depth (Ft) Coordinate with Project Engineer before using this spec.



DIVISION SEVEN - STRUCTURES

FUSP
Code
TitleDate
Modified
Pay
Item 
Notes
SP706AGabion Faced MSE Walls4/6/2021Gabion, MSE Retaining Wall, PVC (Syd)This SP is for GABION Faced MSE Walls. Specifies RCOC Gabion Baskets. Be sure to include the following RCOC FUSPs as required for this SP:
- Backfill, Select, RCOC

These items are included in wall and not paid for separately.
- Backfill Select, RCOC
- Coarse Aggregate 1 by 3

SP706BBridge Name Plate 4/6/2021Bridge Name Plate (Ea)
Use on all Bridge Projects with Bridge Name Plate pay item.
SP706CPrecast Wingwalls and Foundations4/13/2021Precast Wingwalls, Furn and Erect (LSUM)Use for precast wingwalls. Requires editing to make project specific.
SP710AConcrete Surface Coatings  Conc Surface Coating, RCOC (LSUM)
Conc Surface Coating, RCOC (Syd)
Consult with RCOC prior to using. Intent is to protect the concrete and increase lifespan. 



DIVISION EIGHT - INCENDENTAL CONSTRUCTION

FUSP
Code
TitleDate
Modified 
Pay
Item
Notes
SP802AConcrete Curb and Gutter, RCOC4/5/2021Curb and Gutter, Conc,To be used anytime standard curb is modified. (Examples: spill out, mountable, roundabout) Include detail in plans.
SP802BDriveway Opening Concrete Detail M4/5/2021Driveway Opening, Det M, RCOC (Ft)Use across commercial drive approaches. Generally not used on side street approaches unless one is needed to maintain drainage. Include detail in plans.
SP802CConcrete Spillway4/5/2021Spillway, Conc, RCOC (Ft)45 degree angle concrete spillway. Do not use shoulder gutter item with this. Include detail in plans.
SP803B Brick, Salv and Replace 4/5/2021Brick, Salv and Replace (Sft)Use with existing brick pavers to be salvaged and reinstalled. Include detail in the plans.
SP803E Detectable Warning Surfaces
11/24/2021Detectable Warning Surface, West Bloomfield Township (Ft)
Detectable Warning Surface, RCOC (Ft)
Use with sidewalk (ADA) for all RCOC projects. Check with city, village, or township to verify correct use of color, material, etc..
SP805A HMA Gutter and Spillways  4/5/2021 HMA Gutter (Ft)
HMA Spillway (Ft) 
Do not use unless approved by RCOC. Clarifies to use materials as specified in the HMA Application Estimate. This may be applicable on PM projects.
SP807AGuardrail, Wood Back4/5/2021Guardrail, Wood Back (Ft)Use whenever guardrail is adjacent to sidewalk. Do not install on GR endings.
SP807BGuardrail Approach Terminal, Type 2M, MSKT4/5/2021Guardrail Approach Terminal, Type 2M, MSKT (Ea)Use whenever MGS type 2 guardrail approach terminal is in the plans. This spec ensures the selection of the MSKT option. MKST Sole Source letter is also necessary to include if using this spec. 
SP807CMSKT Type 2, MASH, Guardrail Approach Terminal Sole Source Letter1/28/2021SOLE SOURCE LETTER for Guardrail Approach Terminal 2M, MSKT (Ea)This letter is required for all MDOT projects using pay item "Guard Rail Approach Terminal Type 2M, MSKT" in the plans. 
SP808AFence, Protective, RCOC 4/5/2021Fence, Protective, RCOC (Ft)Use on bridge/culvert projects with waterways used by watercrafts.
SP810APost, Flexible, Delineator4/5/2021Post, Flexible, Delineator, RCOC (Ea)Used at shoulder/curb transitions and to mark a drainage outlet. Changed from ASTM Type IV to ASTM Type XI. 
SP812B Temporary Barrier Floats and Buoys 11/17/2021 Regulatory Buoy, Closed Area, Temp (Ea)
 Regulatory Buoy, Danger, Temp (Ea)
 Barrier Float, Temp (Ft) 
 
SP813ARiprap4/5/2021Riprap, Plain, RCOC (Syd) Riprap Plan, RCOC (Ton)
Riprap, Heavy RCOC (Syd)
Riprap, Heavy, RCOC (Ton)
Used for outlet protection and stream banks. Revised heavy riprap size to remove overlap in sizes. Also added language to include geotextile liner in the pay items.
SP813BRiprap, Natural Stone 4/5/2021Riprap, Natural Stone (Syd)Used in residential locations for aesthetics. 
SP814A Natural Channel Structures 4/5/2021 Cross Vane (Syd)  As required by EGLE permit. Detail required in plan set. 
SP814BDitch, Plain Cobble4/5/2021Ditch, Plain Cobble, RCOC (Syd)Similar to MDOT's with the following exceptions: Does not allow crushed concrete, and the minimum average size stone is 8 inches (up from the MDOT 3 inches).
SP816A Geocellular Confinement System  4/5/2021Geocellular Confinement System (Syd) Use on slopes with 1:2 or steeper for slope stabilization. This should be approved by RCOC prior to use. 
SP816BReinforced Turf Driveway4/5/2021Reinforced Turf Driveway (Syd)To be utilized for temporary access driveways. Include detail in plans.
SP816CTurf Establishment, Performance, RCOC4/15/2021Turf Establishment, Sod, Performance, RCOC (Syd)
Turf Establishment, (Type) Seed, (Type) Mulch, Performance, RCOC (Syd)
Used for establishment of turf and restoration along roadways after completion of road construction. Note that final acceptance can not happen sooner than 60 days from day of placement. EMR (snake) friendly mix included as "special mulch". Verify acceptance (60days) with Progress Clause. Temp seeding and temp mulch blankets are paid for separately. 
SP822BSinusoidal Centerline Corrugations3/15/2022Sinusoidal Corrugations, Milled, HMA Centerline (Ft) 
Sinusoidal Corrugations, Milled, Conc Centerline (Ft)
**THIS SPEC IS BEING UPDATED**
These are mumble strips, use at the request of RCOC. Verify all pavement marking quantities are included in the contract per TS order of operations if the specifier uses these items. The 'conc' item will be used in HFST locations
SP823AFire Hydrant and Relocation4/5/2021Fire Hydrant Adjustment (Ea)
Fire Hydrant Relocation, Method _ (Ea)
Use this spec for all fire hydrant adjustments and relocations. Include detail sheet in plans  if using spec. Coordinate use with the owner of the water main (township, utility, etc…). 
SP823BAdjusting Water Shutoff or Valve Box 4/5/2021Water Shutoff, Adj, Case _, RCOC (Ea)
Valve Box, Adj, Case _ (Ea) 
 Use spec for all valve box or water shuttoff adjustments.
SP823CAbandon Water Well 4/5/2021Water Well, Abandon (Ea)Use spec for all water well abandons. 
SP850AReconstructing Sprinkler Systems4/5/2021Sprinkler Head, Relocate (Ea)
Sprinkler Head, Replace (Ea)
Sprinkler Line (Ft)
Irrigation Control Box, Relocate (Ea)
Irrigation Control Box, Replace (Ea)
Include for reconstruction of impacted irrigation and control boxes. Site inspection is recommended, to apply appropriate quantities
SP850BTemporary Pavement Repair 4/5/2021Temp Pavement Repair (Syd)
Temp Pavement Repair, Mobilization (Ea)
Do not use on culvert replacements or PM Jobs. Its best used for staged construction or were you maintain traffic on poor pavements. Also include the MDOT pay item "HMA Patch, Rem"
SP850C Calcium Chloride 
4/5/2021 Calcium Chloride (Gal)Used after HMA Crushing and Shaping, discuss with RCOC Project Engineer prior to use.  



DIVISION 10 - CONCRETE MIXTURES 

FUSP
Code
TitleDate
Modified
Pay
Item
Notes
SP1002AAlkali Silica Reactivity of Fine Aggregate used in Portland Cement Concrete4/30/2021N/AInclude in all projects involving concrete work.
SP1003A Quality Control and Acceptance of Portland Cement Concrete5/25/2021 N/AInclude in all projects involving concrete work. 



WARRANTY INFORMATION

FUSP
Code
TitleDate
Modified
Pay
Item
Notes
WAR02Boilerplate HMA and Concrete Pavement Warranty11/1/2018N/AUse on all projects
WAR03Warranty work requirements for HMA pavement11/1/2018N/AInclude in projects with HMA requiring a warranty.
WAR04Warranty work requirements for jointed plain concrete.11/1/2018N/AInclude in projects with Concrete requiring a warranty.
WAR05Pavement Warranty Information11/1/2018N/AInclude in projects with project specific pavement types requiring a warranty.
WAR06Pass-Through Warranty Bonds11/1/2018N/AConditions in which contractor assigns responsibility for warranty obligations.
WAR09Warranty Guidelines8/13/2018N/AGuidelines for Local Agency Pavement Warranty Program.  



TRAFFIC SAFETY (PAVEMENT MARKINGS AND SIGNING)

FUSP
Code
TitleDate
Modified
Pay
Item
Notes
Traffic Safety General Notes

Traffic Safety General Notes2/11/2020 N/ATraffic Safety General Notes for all construction projects. The PDF document can easily be inserted to the plans as an XRef. 
Traffic Safety General Notes - Log Plans Traffic Safety General Notes - Log Plans  2/11/2020N/A Traffic Safety General Notes for all construction projects. This has the same content as the regular general notes, but this one is specifically set up for log plans. 
SP810BPost Hole through Conc. for Steel Post, 10 Inch Diameter 3/11/2021Post Hole through Conc. for Steel Post, 10 inch diaUsed when drilling post holes through concrete.
SP810C Salvage and Erect Street Sign, RCOC 5/11/2021 Salvage and Erect Street Sign, RCOC (Ea) This is to be used for salvaging existing decorative street signs. 
SP810D Street Sign Post 5/10/2021 Street Sign Post (Ea)  
SP811BRaised Pavement Markers (RPM)N/ARaised Pavt Marker, Retrflec, Monodirectional (Ea)
Raised Pavement Marker, Retrflec, Amber, Bidirectional (Ea)
Raised Pavement Marker, Retrflec, Crystal, Monodirectional (Ea)
Used for installation of raised pavement markers, with iron castings and replaceable prismatic retroreflectors for reflecting light from single or opposite directions. 



TRAFFIC OPERATIONS CENTER (TOC) (TRAFFIC SIGNALS)

FSUP 
Code
TitleDate
Modified
Pay
Item
Notes
TOC General NotesTraffic Operations Center General Notes 8/12/2022N/ATraffic Operations Center general notes for all construction projects involving signal work.  
TOC Std. Con. DetailsRCOC Traffic Safety Department Standard Construction Details March 2014N/AIncluded in contract by reference in Traffic Signal Work - Construction Methods special provision (verify this is included in proposal).
Mast Arm DetailsMast Arm Details 2/11/2019N/AUse with Mast Arm Foundation special provision (RCOC20SP820H)
SP818ATraffic Signal Inspection2/12/2022N/AUse on all projects with traffic signals.  
SP818BTraffic Signal Work - Construction Methods3/15/2022N/AUse on all projects with traffic signals.
SP818CConcrete for Traffic Signal Work 2/12/2022N/AUse on all projects with traffic signals and signals concrete.
SP818DSecondary Cable5/7/2021Cable, Sec, 600V, 1, 2/C#4, #6 Ground, RCOC (Ft)RCOC pay item is obsolete. Use MDOT pay item: Cable, Sec, 600V, 1, 3/C#6 (8182238; Ft)
SP818EConduit, Directional Bore 2/12/2022Conduit, Directional Bore, (number), _ inch, RCOC (Ft)Use RCOC version and not MDOT's. 
SP818F Handhole, Round 2/12/2022 Hh, Round, 2 foot Dia, RCOC (Ea) 
Hh, Round, 3 foot Dia, RCOC (Ea)
Pay item specific to Oakland County signals projects. Pay item names have been revised. 
SP818GHandhole, Square  2/12/2022 Hh, Square, RCOC Ask TOC if square handholes will be used on RCOC projects. TOC may eventually eliminate and replace with "Hh, Round, 3 foot Dia, RCOC" special provision.  
SP820ATraffic Signal Backplate, Retrofit2/12/2022Backplate, Retrofit, RCOC (Ea)
Backplate, Retrofit, (number) Section, RCOC (Ea)
Backplate, Retrofit, HAWK, RCOC (Ea)
Backplate, Retrofit, (number) Section, with case sign, RCOC (Ea)
Backplate, TS, Rem, RCOC (Ea)b
Backplates - used on retrofit projects only. 
SP820B Traffic Signal Backplates  2/12/2022 Backplate, TS, RCOC (Ea) Backplates - new installations; material is no longer incidental. 
SP820BBOptical Priority Control System - Infrared 3/10/2022Optical Priority Control System, Infrared, RCOC (Ea)
Optical Priority Control System, Infrared, Rem, RCOC (Ea)
Optical Priority Control System, Infrared, Salv, RCOC (Ea)
 Pay item specific to City of Novi
SP820C Digital / ITS Type NEMA TS2 Cabinet  3/15/2022Cabinet, ITS Type, RCOC (Ea)
Cabinet, ITS Type, Salv, RCOC (Ea)
Cabinet, ITS Type, Delivered, RCOC (Ea)
Cabinet - ITS type is the typical installation. RCOC does not maintain non-ITS type cabinets and should not be specified. 
SP820D Traffic Monitoring Camera 3/15/2022 Camera, Traffic Monitoring, RCOC (Ea)
Camera, Traffic Monitoring, Salv, RCOC (Ea)
Camera, Traffic Monitoring, RCOC, Rem (Ea)
Camera, Traffic Monitoring, Cable Junction Box, RCOC (Ea) 
Traffic Monitoring/CCTV cameras. (RCOC will not supply antenna, spec says "Owner")
SP820ECase Sign (Non-illuminated)2/12/2022Case Sign, __Way, __inch by__inch, Non-Illuminated, RCOC (Ea)
Case Sign, __Way, __inch by__inch, Non-Illuminated, Salv, RCOC (Ea)
Pay item specific to Oakland County signals projects. 
SP820FDigital Traffic Signal Controller  3/15/2022 Controller, Digital Type, Delivered, Modified, RCOC (Ea) Controller - Centracs. 
SP820G Digital Traffic Signal Controller4/11/2022 Controller, Digital Type, Delivered, RCOC (Ea)
Controller, Digital Type, Delivered, SCATS, RCOC (Ea) 
Controller - Provides 2 options of controller manufacturers. 
SP820H Mast Arm Foundation  2/12/2022 Mast Arm Pole Fdn, 6 Bolt, RCOC (Ft) Include RCOC Mast Arm Details if using. 
SP820I Optical and GPS Priority System Control  5/7/2021 Optical and GPS Priority System, RCOC (Ea)
Optical and GPS Priority Control System, Salv, RCOC (Ea)
Optical Priority Control System, Rem, RCOC (Ea)
Pay item specific to City of Troy; City of Novi requires different special provision.. 
SP820J Pedestal, Alum  2/12/2022 Pedestal, Alum, RCOC (Ea)
Pedestal, Alum, Salv, RCOC (Ea) 
Pay item specific to Oakland County signals projects.  
SP820L Pushbutton Support Helix Foundation, Square Tube Adaptor and Post 5/7/2021 Pushbutton Support Helix Fdn and Post, RCOC (Ea)
Pushbutton Support Helix Fdn and Post, Salv, RCOC (Ea)
Pushbutton Support Helix Fdn and Post, Rem, RCOC (Ea)
Pay item specific to Oakland County signals projects. 
SP820M Pushbutton Support Post 2/12/2022 Pushbutton Support Post, RCOC (Ea)
Pushbutton Support Post, Rem, RCOC (Ea) 
Pay item specific to Oakland County signals projects.  
SP820N Span Wire, Box 3/15/2022 Span Wire, Box, RCOC (Ea)
Span Wire, Box, Rem, RCOC (Ea) 
Pay item specific to Oakland County signals projects.  
SP820O Illuminated Street Name Sign - LED (Clearview Highway 2W Font) 2/12/2022Street Name Sign, Illuminated, One Way, _ foot, RCOC (Ea)
Street Name Sign, Illuminated, Two Way, _ foot, RCOC (Ea)
Street Name Sign, Illuminated, Bracket Arm, RCOC (Ea)
Street Name Sign, Illuminated, Rem, RCOC (Ea)
Street Name Sign, Illuminated, Salv, RCOC (Ea) 
Do not use illuminated and non-illuminated special provisions on the same project. 
SP820P Non-Illuminated Street Name Sign 2/12/2022 Street Name Sign, Non-Illuminated, One Way, _ foot, RCOC (Ea)
 Street Name Sign, Non-Illuminated, Two Way, _ foot, RCOC (Ea)
 Street Name Sign, Non-Illuminated, Bracket Arm, RCOC (Ea)
 Street Name Sign, Non-Illuminated, Rem, RCOC (Ea)
 Street Name Sign, Non-Illuminated, Salv, RCOC (Ea) 

Do not use illuminated and non-illuminated special provisions on the same project. 
SP820Q Tether Wire, Box, Bottom 8/12/2022 Tether Wire, Box, Bottom, RCOC (Ea) Pay item specific to Oakland County signals projects. 
SP820R Preformed Traffic Loop System  5/7/2021 Traffic Loop, Presence (Preformed), RCOC (Ea) Used under concrete pavement only. 
SP820S Video Traffic Detection Camera - Remove 5/7/2021 Video Traffic Detection Camera, Rem, RCOC (Ea) Removal only.  



FUSP FOR LOCAL LET ONLY (FOR INTERNAL USE ONLY)

FUSP
Code
TitleDate
Modified
Pay
Item
Notes
Bid Express InstructionsBid Express Instructions 
N/ADo not put in plans or proposal. It is for information only. 
Itemized Bid Sheet Instructions Instructions to Print Schedule of Items/Itemized Bid Sheet/Blank Bid Sheet N/ADo not put in plans for proposal. It is for information only.  
ChecklistChecklists and Proposal Book Order

N/AFor information only, does not go into proposal book. 
ADMIN1Contract Administration Requirements (Cover Pages)
N/AELECTRONIC ONLY. Use the same information as the paper book title page. All project identifying information is required to be the same on both title pages. This page includes a watermark. 
ADMIN2Advertisement Worksheet
N/AFor Local Lettings only. 
ADMIN2aElectronic Bidding
N/AUse on ALL Local Let projects ONLY. 
ADMIN2bBid Express Bid List Registration
N/AUse on ALL Local Let projects ONLY.
ADMIN5Completion of Designated and Specialty Items
N/AThis replaces the previously used "Subcontractor Requirements" specification. Use if you have subcontractor listed under the prequal lists.
ADMIN6Bid Guaranty
N/AUse on ALL Local Let projects ONLY. 
ADMIN7Payment and Performance Bonds4/27/2021N/AUse on ALL Local Let projects ONLY. 
ADMIN8Indemnification, Damage Liability, and Insurance  N/AUse on ALL Local Let projects ONLY. 
ADMIN9Taxes 4/27/2021N/AUse on ALL Local Let projects ONLY. 
ADMIN10Law Compliance  4/27/2021N/AUse on ALL Local Let projects ONLY. 
ADMIN11Federal E-Verify Program  4/27/2021N/AUse on ALL Local Let projects ONLY. 
ADMIN12Non-Discrimination Clause  4/27/2021N/AUse on ALL Local Let projects ONLY. 
ADMIN13Protection of Wetland and Proper Disposal of Debris  4/27/2021N/AUse on ALL Local Let projects ONLY. 
SP100ALMDOT Standard Specifications for Construction  4/28/2021N/AUse on all road projects that originate from the Engineering Department.
SP100BLDivision One - General Provisions for Local Let Jobs N/AUse on all road projects that originate from the Engineering Department.
SP812AMinor Traffic Devices and Traffic Regulator Control During an Approved Extension of Time 2/5/2021N/AFor Local Lettings only. 
AddendumLocal Let Addendum N/AFor Local Letting only. 
20NB01LNotice to Bidders Contact Person  N/AFor Local Lettings only. 
Inquiry ResponseNotice to Bidders Inquiry Response  N/AFor Local Lettings only. 
Intentionally Blank PageBlank Page (Letter) N/AFor Local Lettings only. 
Intentionally Blank PageBlank Page (Ledger)  N/AFor Local Lettings only. 
2022 Local Letting Dates2022 Local Letting Dates - Planning Guide
N/AFor Local Lettings only. 
2022 Local Letting Dates SID Only
 2022 Local Letting Dates SID Only
  N/A For Local Lettings only



SPECIAL ASSESSMANT DISTRICT (SAD)

FUSP 
 Code
 TitleDate ModifiedPay ItemNotes
20SAD_SP_IndexSpecial Provision Index07/22/2022 N/A
20SAD205A
Ditching, SAD 03/09/2022Ditching, SAD (Ft)
20SAD205B
Excavation, Earth, SAD01/13/2021Excavation, Earth, SAD (Cyd)

20SAD205C
Subgrade Undercutting, Type II, 21AA, SAD01/13/2021Subgrade Undercutting, Type II, 21AA, SAD (Cyd)

20SAD305A
HMA Base Crushing and Shaping01/12/2021HMA Base Crushing and Shaping , SAD (Syd)
Material, Surplus and Unsuitable, Rem, LM (1to 50 Cyd), SAD (Cyd)
Material, Surplus and Unsuitable, Rem, LM (51 Cyd or Greater), SAD (Cyd)

20SAD401A
Pipe Culverts and Storm Sewers01/04/2021

20SAD401B
Culv, Csp Arch, Cl A, 13 Inch by 9 Inch, SAD
Culv, End Section, __ Inch by __ Inch, SAD
010/04/2021Culv, Csp Arch, Cl A, 13 Inch by 9 Inch, SAD (Ft)
Culv, End Section, __ Inch by __ Inch, SAD (Ea)

20SAD403A
Drainage Structure Cover, Type __01/19/2021Dr Structure Cover, Type____, SAD (Ea)
20SAD403B
Drainage Structure, Leaching Basin07/26/2022Dr Structure, Leaching Basin, 48 inch dia, SAD (Ea)
20SAD501A
Pavement Cleaning and Sweeping01/12/2021N/A
20SAD501B
Cement Treated Full Depth Reclamation of Asphalt Pavement07/25/2022Cement Treated Full Depth Reclamation, 12 inch, SAD (Syd)
Cement (Ton)
Removing Excess Pavement Materials, SAD (Syd)

20SAD501C
LKD Pre-Treatment for Full Depth Reclamation07/25/2022LKD Pre-Treatment, 12 inch, SAD (Syd)
Lime Kiln Dust (Ton)

20SAD602A
Concrete Base Course01/06/2021Conc Base Cse, Nonreinf, __ inch, SAD (Syd)
20SAD802A
Mountable Concrete Curb and Gutter01/06/2021Curb and Gutter, Conc, __ inch Mountable, SAD (Ft)
20SAD803A
Brick Pavers04/06/2022Brick Paver, Rem, SAD (Sft)
Brick Paver, Furnished, SAD (Ea)
Brick Paver, Installed, SAD (Sft)

20SAD850A
Hot Applied Joint Sealant, SAD01/12/2021Hot Applied Joint Sealant, SAD (Lb)
Backer Rod, SAD (Ft)

20SAD850B
Water-Dust Control (1,000 Gal Units), SAD01/12/2021Water-Dust Control (1,000 gal units), SAD (Unit)
20SAD850C
Sprinkler Systems01/12/2021Sprinkler Head, Relocate, SAD (Ea)
20SADMOT
Maintaining Traffic for Special Assessment Projects04/08/2022Maintaining Traffic, SAD (Ls)
20SADNB1
Execution and Award of Contract04/06/2022N/A
20SADPC
Progress Clause04/06/2022N/A