Independence Township Road Improvement Millage

Independence Township voters passed a road millage in 2018.  The four-year millage provides funding to resurface virtually every major road in the township. This page provides a list of roads that will be improved.  

Resurfacing projected schedule for 28.4 miles of roads:

2020 (project start dates are subject to change; work is weather-dependent):


  • Andersonville Road,from Old White Lake Road to the township border  (May 8 start and expected completion late June)COMPLETE
  • Clintonville Road, from Maybee Road to township line Mann Road (August 4 expected start)  COMPLETE
  • Clintonville Road, from Waldon Road to Clarkston Road (July 21 expected August 5 through August 26 and will include road closure to through traffic; residential and business access maintained)
    • Detour for through traffic:  Pine Knob Road to Sashabaw Road to Clarkston Road, back to Clintonville Road and vice versa
    • PRESS RELEASE: CLICK HERE
  • Clintonville Road, from Maybee Road to Waldon Road (August 26 trough Sept. 23 and will include road closure to through traffic; residential and business access will be maintained)
    • Detour for through traffic: Maybee Road to Sashabaw Road to Clarkston Road, back to Clintonville Road and vice versa.
    • PRESS RELEASE:  CLICK HERE
  • Sashabaw Road, from south of Clarkston Road (DTE)  to Oak Hill Road (township limits) (June 29 is the start date) *temporary striping will be placed until work on Sashabaw Road over the Whipple Lake canal is completed.   SUBSTANTIALLY COMPLETE
  • Sashabaw Road, from Maybee Road to the township border (July 13 expected start for resurfacing work; preliminary work begins July 9)  COMPLETE
  • Waldon Road, from the village limit to Clintonville Road (May 26 -early July, road closed to through traffic; residential and business access will be maintained)  SUBSTANTIALLY COMPLETE & OPEN TO TRAFFIC 
    • Detour for through traffic:  Sashabaw Road to Maybee Road to Clintonville Road, back to Waldon Road and vice versa.
    • Press release:  CLICK HERE


(note:  Flemings Lake Road paving has been moved to 2021 due a conflicting school project)

CONTRACTOR:  Cadillac Asphalt 

Contractor website:  https://www.cadillacasphalt.com/

Start date:  May 4, 2020 May 11, 2020 (changed by the Contractor)

End date:  Late summer/early fall  for paving; early October for restoration work (typically work done behind the road shoulder)

2021:

  • Clarkston Road, from the Village limits to the Orion Township border
  • Flemings Lake/Walters Road, from Clarkston Road to Waldon Road
  • North Eston Road, from Clarkston Road to pavement end
  • White Lake Road, from the Village limits to Andersonville Road

2022:

  • Holcomb Road, from the Village limits to the Springfield Township border
  • Maybee Road, from Dixie Hwy to the Orion Township border


Independence Township Road Improvement Millage Information: CLICK HERE

RCOC Praises Community Road Millage Efforts:  CLICK HERE


Additional information:

Waldon Road between Clintonville and Sashabaw roads expected to close through traffic from May 26 through late June

REVISED START DATE:  2020 Independence Road Millage paving set to begin May 8 with Andersonville Road

2020 Independence Township Road Millage paving set it begin May 11 starting with Andersonville Road

Independence Township Road Millage Improvements