12 Mile/Novi Road Intersection - 2019

IMG_0137

Community:  Novi

  • Comments:  Novi Road and 12 Mile Road concrete replacement project
  • Project cost:  Approximately $1.1 million 
  • Funding sources:  Federal aid, RCOC and the City of Novi
  • Project includes:
    • Removing and replacing concrete
    • Reconstruction of the 12 Mile turnaround just west of Novi Road 
    • Replacing Novi Road approaches at 12 Mile Road
    • Americans with Disabilities Act-compliant sidewalk ramps and upgrades to pedestrian signal
  • Contractor:  Mark Anthony Contracting
  • Start Date:  June 17 
  • End:  Mid-August  Mid-September 
  • ALL BUSINESS ACCESS MAINTAINED DURING CONSTRUCTION 
  • Road Closure:  Yes.  Northbound and southbound Novi Road will close at 12 Mile Road.  Date to be announced.  12 Mile Road will have one-lane open in each direction.
  • Detour:   For the closure of the Novi Road approaches to 12 Mile (date TBA)  Grand River Avenue to Meadowbrook Road to 13 Mile Road, back to Novi Road

12 Mile & Novi Progress Photos

Additional Information:

PHASE 2 Construction begins Aug. 2 with northbound and southbound Novi Road approaches at 12 Mile Road closing

Hometown Life article on 12 Mile/Novi Road intersection reconstruction (6/14/19)

12 Mile/Novi Road intersection reconstruction will begin Monday, June 17

Oakland Press article on the road construction (5/14/19)


Novi/12 Mile Road construction staging map (provided by the City of Novi)