Adams/Gunn Road Roundabout - 2019

  • Community: Oakland Township
  • Comments:  Construction of a roundabout at the Adams and Gunn Road intersection
  • The $2.574 million project is funded by a federal safety grant ($600,000), RCOC ($1,474,000), Tri-Party Program ($252,746) and Oakland Township ($247,254).
  • The project includes:
        -Reconstruction of the intersection to a roundabout
        -Resurfacing Gunn Road from Adams to a half-mile east of Adams
        -Improved drainage
        -Installation of curbs and gutter
        -High Intensity Activated Crosswalk (HAWK) pedestrian crossing beacons/crosswalks at the north leg of the roundabout

Adams/Gunn Road Roundabout Construction Progress Photos:

 CLICK HERE


Adams/Gunn Road Roundabout Construction Work Zone Camera Time-lapse Video:  CLICK HERE

Adams and Gunn Road intersection prior to construction

Adams Road Bridge Work Over Paint and Trout Creeks

  • Paint and Trout Creek Bridges
  • Community: Oakland Township
  • Funding: project estimate is $450,000
  • Bridge preventative maintenance includes:
- Repair of bridge approaches
- Epoxy overlay on bridge deck
- Paving with hot mix asphalt 
- New guardrails
Contractor, timeline and detour:
  • Contractor: Florence Cement Company
  • Start Date: June 17 work will be done after the Adams/Gunn Road closure for roundabout construction
  • End Date:  August 28, 2019
  • Detour: Yes; however, residential access is maintained north of Gunn Road.  Through traffiic detour is  Silverbell Road to Orion Road, back to Adams Road and vice versa.
Progress Photos

IMG_2892

Additional Information:

Press Release on Start of Roundabout

Adams and Gunn Road Roundabout Construction Work Zone Camera

Adams Road Bridge Maintenance Press Release


​Articles:

C&G article on RCOC recommending roundabout for Adams/Gunn Road intersection (9/26/17)

Oakland Press article on RCOC recommending roundabout at the Adams/Gunn Road intersection (10/6/17)

Rochester Media story on Adams/Gunn Road 4-way stop (7/23/16)

Oakland Press article on Adams/Gunn construction (6/7/19) **may need a password for access

Oakland Press article on the beginning of the Adams/Gunn Road Roundabout construction (3/28/19)

Oakland Press article regarding Gunn/Adams Road (4/12/18)

​Other:

Adams/Gunn Road May 8 Public Meeting for 2019 Intersection Improvement Project

Adams/Gunn Road Project Information Flier 

Adams/Gunn Road intersection converted to a 4-way stop as an interim safety improvement (8/22/16)



​Detour Map:


Adams Gunn Detour Route_3-26-19