Tripp Road

  • Project Limits: Dixie Highway to Van Road
  • Community: Groveland Township
  • COMMENTS:     
$2.3 million project is funded by the RCOC, Groveland Township and Oakland County general government through its Tri-Party Program
  • Complete reconstruction
  • Installation of curb and gutter
  • Shoulder widening
  • Improved drainage
  • Replacement of the Thread Creek culvert
  • Tree removal in the right of way begins Feb. 13, 2018; with traffic under flag control when necessary.  Trees are removed in the winter per federal guidelines that protect the Northern Long-eared Bat and the Indiana Bat, both are on the national endangered species list.    Trees need to removed by March 31.  Tree trunks and stumps will be removed when the project starts in the summer of 2018.    Utility work is also on-going in anticipation of the project.  

  • Contractor: Angelo Iarate
  • Start Date: July 30, 2018
  • End Date:   Late November
  • Detour: Yes, Dixie Hwy to Grange Hall Road back to Trip Road and vice versa (residential access maintained throughout the project)
Additional Information:

Photo Gallery: Tripp Road


Tripp Road Construction to begin July 30;  road will close to through traffic

Tripp Road Public Meeting scheduled for Wednesday, December 6, 2017

Tripp Road Project Information Flyer

Oakland Press article on public meeting (12/5/17)

Tripp Road sign

Tripp Road prior to construction