Dequindre Road (2017-2018)

  • Road: Dequindre Road
  • Project Limits: Long Lake Road to Burningbush Drive
  • Communities: Troy and Sterling Heights
  • Comments:
    • Project cost is $16.5 million funded mostly by federal funding, RCOC, Macomb County Department of Roads, Troy and Sterling Heights
    • Road widening from 2 lanes to 5 lanes of Dequindre Rd. (Long Lake Rd. to Burningbush Dr.)
    • Reconstructed road will include 2 through lanes in each direction and a continuous center left-turn lane and right-turn lanes at major intersections
    • New concrete curbs, curb and traffic signals
    • Significant drainage improvements
    • Americans with Disabilities Act (ADA) compliant crosswalks
  • Contractor: Dan's Excavating
  • Phase 1 Start Date:  September 18, 2017
  • Phase 1 End Date:  November 8, 2017 
  • Phase 2 Start Date:  Monday, March 5, 2018
  • Anticipated Project Completion:  Late Fall of 2018
  • Closure:  Yes, the west half of the Square Lake/19 Mile Road and Dequindre Road intersection will close on May 21, 2018 through approximately June 21, 2018 for paving.  Northbound and southbound Dequindre Road and eastbound Square Lake/19 Mile Road will remain open.  For details:  Click here

Dequindre Road and Square Lake/19 Mile intersection to close Oct. 17-Nov. 15 for storm sewer work/Opening November 8, ahead of schedule!   

Dequindre Road Detour (Oct. 17-November 15)

Dequindre Road Construction between Long Lake Road and Burning Bush Drive will begin on September 18, 2017

Second public information meeting for Dequindre Road construction to take place on Aug. 22

Project Public Meeting Flier

Public Meeting Press Release

Dequindre Road Closure Press Release

C and G Article on Dequindre Road Project (Sept 5, 2017)

C&G News September 27 article on Dequindre Road construction


Dequindre and Square Lake