Maple Road - Orchard Lake to Farmington

  • Road:   Maple Road (2-year project) COMPLETE
  • Project limits:   (Phase 1) 2016-Farmington Road to Drake Road, including Farmington/Maple roundabout    
  • Project limits (Phase 2):   2017-Farmington Road and Orchard Lake Road (BEGINS APPROXIMATELY APRIL 3, 2017
  • Community:  West Bloomfield Township
  • Comments:
    • The $6.4 million project covers 1.8 miles and includes:
      • Rehabilitation and resurfacing of Maple Road from Drake Farmington Road to Orchard Lake Road
      • Addition of a continuous center, left-turn lane
      • Right-turn lane extensions in several areas
      • Paved shoulder widening
      • Improved drainage
      • Curb and gutter installation
      • Traffic signal modernization
      • Americans with Disabilities Act (ADA) compliant pedestrian crosswalks
      • Work at the Farmington/Maple Road roundabout (milling, resurfacing and installation of HAWK pedestrian crossings) COMPLETE
  • Contractor:   Dan's Excavating
  • Start date for second segment:   April 3, 2017 (PHASE 2)
  • End date:  Road open to traffic on July 14, 2017

Additional Project Information:

Oakland Press article on EB Maple Road closure (3/31/17)

Phase 2 Construction on Maple Road from Farmington to Orchard Lake Road begins April 3, 2017

Maple Road Construction Photo Album

Maple Road article (5/12/16)


RCOC Gears Up for $27 Million in road projects (4/3/16)

Maple Road Construction article (4/19/16)

MI Road Construction article 4/19/16)

Maple Road article (3/30/15)

Eastbound Maple from Drake to Farmington to Close Press Release (7/7/16)

Maple Road Public Meeting
 
Maple Road Project Flier
 
IMG_0256
 
 
 
 
   Maple Road Closure Sign