Barron Road

Barron Road Public Information Meeting
 Tuesday, November 12, 2019
 4:00 p.m. to 7:00 p.m.

Groveland Township Hall, 4695 Grange Hall Road, Holly, MI 48442 (Map)

Project Limits: Grange Hall Road to Groveland Road

Community: Groveland Township

Comments:

The approximately $5.5 million project is mostly federally funded, with the remaining portion shared by Road Commission for Oakland County, Groveland Township and Oakland County general government (through the Tri-Party program).  The project includes:

  • Paving 2.39 mile section of gravel road with asphalt
  • Placing concrete curbs and gutters
  • Installing storm sewers to improve drainage
  • Improving the driving sight distance
  • Utility relocation starting in 2020 
  • Tree removal (expected December 1, 2020-late December)
Contractor:  Iafrate Construction 

Construction start:   April 16, 2021 (approximate)

Anticipated completion:  mid-November

Road closure:  Yes, residential access maintained.  Detour: Grange Hall Road to Jossman Road to Groveland Road, back to Barron Road and vice versa.  


ADDITIONAL INFORMATION:



Project Meeting Flier

Barron Road paving public information meeting to take place on Nov. 12, 2019

Barron Road and Grange Hall Road sign

Barron Road south of Grange Hall Road (gravel road photo)