Concrete Slab Replacement

The Road Commission for Oakland County is planning concrete slab replacement on many roads in 2018.  In 2017, over $4 million in concrete slab replacement projects were completed on roads throughout Oakland County.     Traffic will be maintained; however, there will be lane closures staged throughout each project.  Concrete can take up to 10 days to cure before allowing traffic back on it.  Work is also material, equipment and weather-dependent.

Here is a list of the upcoming projects, keep checking back for updates.  

Concrete Slab Replacement 2018 Project List 

Road/Intersection

Project Limits 

Community or Communities 

Approximate Start 

Approximate
Completion
 


Contractor 

10 Mile Rd Orchard Lake Rd to Elmhurst Ave Farmington TBD TBD Cipparone
10 Mile Rd Inkster Rd to Stony Creek Dr Farmington Hills TBD TBD Cipparone
WB 10 Mile Rd (696 Service Dr) Church St to Gardner St Oak Park TBD TBD Cipparone
EB 10 Mile Rd (696 Service Dr) Gardner St to Cloverlawn St Oak Park TBD TBD Cipparone
10 Mile Rd (696 Service Dr.) Turnaround East of Gardner St Oak Park TBD TBD Cipparone
10 Mile Rd/696 Service Dr Guthrie Ave to Helene Ave Royal Oak TBD TBD Cipparone
12 Mile Rd Novi Rd to Carlton Way Dr Novi 6/11/18 TBD Cipparone
12 Mile Rd Meadowbrook Rd to M-5 Novi TBD TBD Cipparone
14 Mile Rd Greenfield Rd to Southfield Rd Beverly Hills TBD TBD Cipparone
Greenfield Rd S/o I-696 to N/o Lincoln Dr  Southfield 6/14/18   Cipparone
SB Haggerty Rd Right hand turn lane North of 12 Mile Rd Farmington Hills Late May (further work on 6/22/18) TBD Cipparone
Livernois Rd Big Beaver Rd to I-75 Troy TBD TBD Cipparone
South Blvd I-75 to Old Chatham Dr  DETOUR MAP Bloomfield Twp 6/4/18  (requires road closure) Open on 6/18 (further milling and paving work on side street entrances is pending) Cipparone
Southfield Rd 14 Mile Rd to 12 Mile Rd and 10 Mile Rd intersection Beverly Hills and Southfield TBD TBD Cipparone
Waldon Rd EB and WB approach to Sashabaw Rd Independence Twp TBD TBD Cipparone
West Long Lake Road Corporate to Tower Drive Troy 6/18/18 Late July Rigid Pavement Corporation

​Additional Information:



South Blvd to close between Squirrel and Opdyke roads on June 4 for approximately 10 days





Concrete Slab Replacement 2017 Project List

Road/Intersection

Project Limits

Community or Communities

Approximate Start

Approximate
Completion


Contractor

12 Mile Road

Haggerty to Farmington Rd

Farmington Hills

8/14/17

Substantially Complete

Florence Cement
Company


Sashabaw Road

Maybee to Waldon Rd

Independence Twp

7/27/17

COMPLETE

Cipparrone
Contracting

Brown Road

Joslyn Road to M-24

Auburn Hills/Orion Twp

8/24/17

COMPLETE

Cipparrone
Contracting


Cass Lake Road

Orchard Lake to Otter Ave

Keego Harbor

8/14/17

COMPLETE

Cipparrone
Contracting


Haggerty Road

10 Mile intersection

Novi/Farmington Hills

7/24/17

COMPLETE

Cipparrone
Contracting


Greenfield Road

9 Mile to 10 Mile Rd

Southfield

9/28/17

COMPLETE

Cipparrone
Contracting


Southffield Road Southbound lane both north and south of 10 Mile Rd; including 10 Mile Rd eastbound approach to Southfield Southfield 11/06/17 COMPLETE Cipparrone
Contracting


Southfield Road 12 Mile Rd to 13 Mile Rd Southfield 11/06/17 COMPLETE Cipparrone
Contracting


 12 Mile Road
East of Telepgraph (westbound outer lane by dealership)
Southfield 11/1/17
SUBSTANTIALLY COMPLETE Cipparone Contracting
Novi Rd to Carlton Way Dr
Novi Rd to Carlton Way Dr