Groveland Road-COMPLETE

  • Road:  Groveland Road
  • Project limits:   Jossman Road to M-15
  • Community:  Groveland Township
  • Comments:
    • Groveland Road from Jossman Road to M-15 is scheduled for preventative maintenance is COMPLETE.  
      • Overband crack filling
      • Pavement repairs
      • Single course chip seal
  • Contractor:  Pavement Maintenance Systems
  • Start date:  Early June
  • End date:  Mid-June COMPLETE