Adams Road Bridge Over Clinton River COMPLETE

  •  Road:    Adams Road Bridge over Clinton River
  • Project limits:   Adams Road north of Hamlin Road
  • Community:  Rochester Hills
  • Comments:
    • Preventative maintenance project to extend life of the bridge; $339,000 project includes:
      • Bridge deck rehabilitation
      • Hot Mix Asphalt paving (HMA)
      • Waterproof membrane to preserve bridge deck
      • Guardrail installation
  • Contractor:  Pavex Corporation
  • Detour:  Yes
  • Detour route:   Hamlin Road to Crooks Road to Avon Road back to Adams Road and vice versa
  • Start date:  July 11, 2016
  • End date: COMPLETE