Maple Road (Walled Lake)-COMPLETE

  • Road:   Maple Road
  • Project limits:  Pontiac Trail to Welch
  • Communities:   Walled Lake and Commerce Township
  • Comments:
    • Maple Road is scheduled to have overlay work done in 2016 as part of the RCOC preventative maintenance program.
    • Project length is .91 miles
    • Project cost is estimated at $1 million
    • Project includes:
      • Hot mix asphalt cold milling and resurfacing
      • Drainage improvements
      • Behind the curb decorative concrete (funded by Walled Lake)
      • Concrete curb and gutter
      • Americans with Disabilities Act (ADA) compliant sidewalk, ramps and pedestrian signal
  • Contractor:   Cadillac Asphalt
  • Detour:  No, road will remain open during construction
  • Start date:  May 31, 2016
  • End date:   SUBSTANTIALLY COMPLETE ON 8/2/16

Maple Road Construction Photo Album

Maple Road Project Press Release